LESCO new connection/ Meter Transfer Procedure

LESCO new connection | New meter connection status 2024

Lesco new connection procedure is easy and simple. If you do not have an electricity connection and you are living in Lahore or the surrounding of Lahore, you need a new electricity connection. You have applied for a LESCO new connection and also you can check the new meter connection status where the process has reached.

Procedure to apply for new electricity connection

If you are living in Pakistan and you want a new electricity connection, there is no need to worry. In this guide, we will explain briefly how to setup a new electricity connection. Additionally, you can check Lesco bill online. The new electricity connection application form is attached here.

LESCO new connection procedure

The process of a new electricity connection from Lesco involved several steps. All these steps are explained briefly:

Application Submission:

There are two ways to get an application form to apply for LESCO new connection. First, you can visit the nearby Lesco office to get the application form or you can download it from the above link. Fill out the application form with all essential details including personal information and the type of connection required such as domestic, industrial, or commercial.

Documents submission

The following documents are required to apply for a new Lesco meter connection.

  • Attested copy of the applicant’s CNIC
  • Proof of property ownership
  • NOC certificate
  • Two CNIC attested copies of witnesses or neighbors
  • A copy of the tariff duly signed by the new customers.
documents required for LESCO NEW CONNECTION

If you are going offline, you need to get a printed copy of the application form attach all the above documents with the application form, and submit it to the Lesco concerned office.he above documents with application form and submit to the lesco concerned office.

Site Survey:

Based on the feasibility report and verification of documents, LESCO will issue a demand notice to the applicant, specifying the charges for the new connection. The applicant will get Lesco’s new connection demand notice print. Further, he has to pay the LESCO demand notice amount at the designated bank.

Demand Notice Issuance:

Based on the feasibility report and verfication of documents, LESCO will issue a demand notice to the applicant, specifying the charges for the new connection. The applicant will get Lesco new connection demand notice print. Further, he has to pay LESCO demand notice amount at the designated bank.

New meter installation

Once the payment is confirmed, LESCO will schedule the installation of the electricity meter and connection. The LESCO team will install the meter and complete the connection.

Connection Activation:

LESCO may conduct a final inspection to ensure compliance with all requirements. The connection will be activated, and the electricity supply will commence.

Tips for a Smooth LESCO New Connection Process:

  • Ensure all forms are correctly filled out and all required documents are attached.
  • Pay the demand notice promptly to avoid delays.
  • Follow up with LESCO customer service if there are any delays or issues.

Lesco new connection tracking

There are several ways to track new connection applications. Each is explained below:

Online Tracking:

You can simply check the new meter connection status online by following the steps given below:

  • Visit the electricity new connection system (enc)
  • Look for the new connection application section or navigate to customer services.
  • Enter the application number of the new electricity connection given by LESCO during the application submission.
  • After doing this system will display the application status.

Offline tracking by visting Customer Service Centers:

Visit the nearest customer service center with the application number given by LESCO. Provide the details of the application number and ask for LESCO new connection tracking. The customer service center representative will provide you with the current status of your LESCO new connection application.

Helpline

Call the helpline to check Lesco’s new connection application. This is helpline number 111-000-118. Provide the application number and ask for application tracking. They will check the status in their system and inform you accordingly.

LESCO Meter Transfer Procedure

The following steps are included in the LESCO meter transfer procedure,

  • First of all, you have to collect the required documents. For this purpose, you must have an application for meter transfer. This application can be obtained from the LESCO office or their official website. You must have a copy of the CNIC of both the current and new owner, proof of ownership, previously paid bills, a No Objection Certificate (NOC) from the current owner, and an Affidavit (agreement between both parties).
  • The second step is the submission of the application. Visit to nearest LESCO customer service center with all required documents. There you would have to fill out the given application form and submit it along with all required documents. Then LESCO will verify whole details provided in the application. After it LESCO team may visit to verify the location and other relevant details. 
  • LESCO may issue transfer fees before processing. Pay the fees through the available payment method. After confirmation of payment, LESCO starts the process of meter transfer. After that, LESCO will approve the meter transfer and update their records.
  • In the last step, the new owner will receive a confirmation letter from LESCO, and also future electric bills will be issued in the name of the new owner.
  • With these given steps, you can easily transfer the LESCO electricity meter to the new owner’s name. 

How to check demand notice?

If the client’s new connection application for Lesco has been accepted, LESCO will issue the demand notice.  LESCO customer care center issues the demand notice and customers can receive this by a post office.
The applicant has to write an address on the application. LESCO issues the demand notice on the written address. Some people are curious about WAPDA demand notice tracking but I’m here to confirm that WAPDA has a regional power supply company such as LESCO. These regional companies issue the demand notice to the applicants.

FAQ’s

Q1: How can I apply for a LESCO new connection in 2024?
A: You can apply for a new LESCO connection by visiting the official LESCO website and filling out the online application form. You will need to provide personal information, property details, and the required documents for processing.

Q2: What documents are required for a new LESCO meter connection?
A: Typically, the required documents include a copy of your CNIC, property ownership documents or rent agreement, a recent utility bill (if applicable), and a completed application form. Be sure to check the LESCO website for a full list of requirements.

Q3: How can I check the status of my new LESCO meter application?
A: To check the status of your new meter application, visit the LESCO website and go to the “Application Status” section. Enter your application number, and the system will show the current progress.

Q4: What is the cost of a new meter connection with LESCO in 2024?
A: The cost varies depending on the type of connection and usage requirements. For the most accurate fee information, check LESCO’s latest tariff and connection fee guidelines on their website or contact customer service.

Q5: How long does it take to get a new LESCO meter connection?
A: After submitting the application and documents, the processing time may vary. Typically, it can take a few weeks, but factors such as property location, inspection, and approval may influence the timeline.

Conclusion

The installation of LESCO’s new connection is an easy and simple method. In the above, we have explained in complete detail how to apply for a new electricity connection and the documents required for a new meter connection. We have given full details of Lesco’s new connection tracking and about Lesco’s demand notice tracking. If you have any queries about the new meter connection status, you can contact us.

Similar Posts

Leave a Reply

Your email address will not be published. Required fields are marked *